Baseline Monitoring Report (Rev. 3)
for
Mai Po Nature Reserve Infrastructure Upgrade
Project (Environmental Permit No. EP-598/2022)
July 2023
(Version 3.0)
Certified By Environmental Team Leader:
(Joan Choi)
Company: Ka Shing Management Consultancy Ltd.
Table of Content
Page
No.
EXECUTIVE SUMMARY
1. PROJECT BACKGROUND ...................................................................................... 1
2. ECOLOGY ................................................................................................................ 2
3. LANDSCAPE AND VISUAL ..................................................................................... 3
3.1 Baseline Review of Landscape and Visual Conditions ..................................... 3
3.2 Methodology of Baseline Review .................................................................... 12
3.3 Findings .......................................................................................................... 13
3.4 Conclusion ...................................................................................................... 22
4. WATER QUALITY .................................................................................................. 23
4.1 Monitoring Requirements ................................................................................ 23
4.2 Event / Action Plan ......................................................................................... 24
4.3 Monitoring Procedure ..................................................................................... 26
4.4 Data Management and QA/QC ....................................................................... 27
4.5 Discussion and Recommendations ................................................................ 28
List of Appendices
Appendix A Location plan and site layout plan of the Mai Mai Po Nature Reserve
Infrastructure Upgrade Project.
Appendix B Photographic comparison of baseline condition of Landscape Resources (LRs)
between EIA Stage and Present (3
rd
, 4
th
& 24
th
March, 2023).
Appendix C Photographic comparison of baseline condition of Landscape Character Areas
(LCAs) between EIA Stage and Present (3
rd
, 4
th
& 24
th
March, 2023).
Appendix D Baseline tree photo records with tree survey plan and tree assessment schedule
conducted between 10
th
& 13
th
March, 2023.
Appendix E Photographic comparison of photomontages VP01 to VP07 between EIA stage
and Present (3
rd
March, 2023).
Appendix F Tree Information included in App. D of Approved EIA Report.
Appendix G Tree Schedule and Survey Plan prepared for the Tree Preservation and Removal
Proposal on March 2022.
Appendix H Layout plans showing the approved monitoring locations.
Appendix I Calibration certificates of equipment used.
Appendix J Supplementary Meteorological Data.
Appendix K Water Sampling Data Record
EXECUTIVE SUMMARY
1. Ka Shing Management Consultancy Ltd. has been commissioned by the World Wide Fund
for Nature Hong Kong (“WWF”) to undertake the assignment as the Environmental Team
(ET) for the Designated Project of Mai Po Nature Reserve Infrastructure Upgrade Project.
This Baseline Report is prepared by Ka Shing Management Consultancy Ltd for Contract.
2. The Project under Mai Po Nature Reserve Infrastructure Upgrade Project (Register No.
AEIAR-233/2022) is approved by the Environmental Impact Assessment (EIA) report and
later granted an Environmental Permit (EP) (Permit No. EP-598/2022). The approved EIA
report described both the construction phase and operational phase.
3. According to the approved Environmental Monitoring & Audit (EM&A) Manual, ET
checks will be conducted during the breeding season to check for the presence of breeding
ardeids within 500m of the footprint of project elements. These checks should be carried
out two weeks prior to construction commencing and the day before.
4. Prior to the commencement of construction works, a Baseline Landscape and Visual Report
shall be prepared to check, record and report the status of the Landscape Resources (LRs)
and Landscape Character Areas (LCAs) within the works areas and the Visually Sensitive
Receivers (VSRs) within the visual envelope. The Landscape and Visual Impact
Assessment (LVIA) in the EIA Report may be used to formulate the Baseline Monitoring
Report provided that there have been no significant changes to the status of LRs, LCAs
and VSRs since the approval of the EIA Report. The baseline landscape condition of the
areas within and adjacent to the described proposed TH2 and TH3 remains unchanged
since the EIA stage. The views of the Project site and adjacent areas from identified VSR
are also expected to have remained unchanged.
5. The construction water quality monitoring is required to be performed during the
construction phase of the Project. As part of the EM&A programme, baseline monitoring
is required to determine the ambient environmental conditions. Prior to the commencement
of construction work of the Project, baseline water quality at all designated monitoring
stations was carried out from 4th March 2023 to 29th March 2023.
1 | Page
1. PROJECT BACKGROUND
1.1 The Mai Po Nature Reserve has served Hong Kong as one of the most valuable ecological assets
in the city, and is managed by the World Wide Fund for Nature Hong Kong (“WWF). WWF
proposes to update of an existing concrete footpath of about 1.5m wide to a raised wooden
boardwalk of about 1.65m wide, construction of a new three-storey tower hide (TH2) and the
associated access wooden boardwalk of about 156m long and 1.65m wide; and construction of a
new three-storey tower hide (TH3) and the associated access wooden boardwalk of about 85m
long and 1.65m wide. The location of the Project as shown in the Appendix A of this report.
1.2 The project site is located in Mai Po Nature Reserve (MPNR) where has been managed by World
Wide Fund for Nature Hong Kong (“WWF”) since 1984. More than 20,000 people per year
visiting the MPNR and growing in visitor numbers is anticipated. Most of the existing facilities
have been in use for more than 20 years, in order to cater for an increasing number of visitors and
providing the good condition of facilities in the future, the upgrade of infrastructure is proposed.
The WWF had completed an Environmental Impact Assessment (EIA) and is the Permit Holder.
1.3 The Project under Mai Po Nature Reserve Infrastructure Upgrade Project (Register No. AEIAR-
233/2022) is approved by the EIA report and later granted an EP (Permit No. EP-598/2022). The
approved EIA report described both the construction phase and operational phase.
1.4 Ka Shing Management Consultancy Ltd. has been commissioned by the WWF to undertake the
assignment as the Environmental Team (ET) for the Designated Project of Mai Po Nature Reserve
Infrastructure Upgrade Project.
1.5 In accordance with the Project EM&A Manual requirements, water quality monitoring,
ecological monitoring, and site inspections should be covered in this Contract. Overall, the
EM&A works follows the demarcation of monitoring responsibilities.
1.6 The objective of this Baseline Monitoring Report is to determine the baseline levels of the
environmental aspect of water quality, ecology, landscape and visual issues around the Project
area prior to the commencement of any construction works of the Project.
1.7 The Baseline Monitoring Report presents the details of baseline study including project
background, monitoring methodology, monitoring results, summary of findings and Action/Limit
Levels (AL/LL) established for subsequent use in the Project construction phase EM&A
programme.
2 | Page
2. ECOLOGY
2.1 Pursuant to Condition 2.11 of the Environmental Permit (EP) (Permit No.: EP-598/2022), The
Permit Holder shall, no later than one month before the commencement of construction of the
Project, carry out on-site inspection within 500m of the footprint of project elements (i.e. TH2,
TH3 and the boardwalk) to confirm whether egretry and breeding ardeids is identified at a
distance that may be affected by the construction works of the Project.
2.2 The on-site inspection under requirements of the EP for an Egretry Mitigation Measures Plan
(EMMP) was conducted on 7 March 2023, which fell within the breeding season of ardeids in
Hong Kong. The inspection has covered all the accessible paths within 500m study area of the
footprint of project elements, with particular focus on the potential nesting area of ardeids (e.g.
bamboos and native/exotic trees). The general view of the study area is shown in Figure 1. During
the inspection, no nest and breeding behavior of ardeids such as nest sitting and chick feeding
were observed within 500m study area.
2.3 The survey was conducted within 500m study area of the footprint of project elements (i.e. TH2,
TH3 and the boardwalk) (Figure.1). The survey was started from 9:00 am and lasted for more
than three hour. During the survey, the egretry was scanned by the surveyor by using binoculars
(Minox 8x42 binoculars). Ardeids breed between March and August in Hong Kong. All active
nests were identified and recorded. Aside from bird nests, any activities related to breeding
behaviour, such as nest sitting and chick feeding, were also recorded. The species composition
and abundance of the breeding ardeids community were recorded.
2.4 As required by the section 6.2.7 of the EM&A Manual, ahead of construction ET checks will be
conducted during the breeding season to check for the presence of breeding ardeids within 500m
of the footprint of project elements. These checks should be carried out two weeks prior to
construction commencing and the day before. Should any egretry be discovered in the vicinity
of works areas, the need for mitigation measures shall be assessed in consultation with
Agriculture, Fisheries and Conservation Department of Hong Kong. Observation will be updated
in the coming Monthly E&MA Report.
2.5 The egretry was scanned by the ET by using binoculars (Minox 8x42 binoculars) and no nests
were found within 500m study area of the footprint of project elements (i.e. TH2, TH3 and the
boardwalk) on 7 March 2023. When there are ongoing construction works within the Project Site,
the ET shall carry out inspections once per week and the IEC shall carry out audits jointly with
the ET once every two weeks throughout the construction period. Inspection findings shall be
logged in a site monitoring report with any discrepancies or concerns regarding the
implementation and effectiveness of mitigation measures highlighted.
3 | Page
3. LANDSCAPE AND VISUAL
3.0.0 Baseline Landscape and Visual Report aims to record the baseline conditions associated
with the construction of Footpath and Tower Hides at MPNR, and compare with the
relevant Landscape Resources (LRs), Landscape Character Areas (LCAs) and Views of the
Visual Sensitive Receivers (VSRs) identified in the EIA Report and EM&A Manual for
Mai Po Nature Reserve Infrastructure Upgrade Project.
3.0.1 This baseline monitoring report shall be submitted to the Director of Environmental
Protection Department at least 2 weeks before the commencement of the Project.
3.1 Baseline Review of Landscape and Visual Conditions
Review of the Approved EIA Report and fulfil the requirement of Section 8.3 of the EM&A
Manual.
3.1.1 The approval of EIA Report AEIAR-233/2022 Mai Po Nature Reserve Infrastructure
Upgrade Project has been reviewed to extract relevant information about the baseline
conditions of the landscape resources, landscape character of the area and visual sensitive
receivers during the EIA stage.
Landscape Resources (LRs)
3.1.2 At the EIA stage, three landscape resources categories were identified within the project
site which was identified as, LR1 Vegetation, LR2 Water Bodies (Hydrology) and LR3
Planting Surrounding Development Area. Both LR1 & LR2 were further sub-divided into
relevant sub-categories and the identified Landscape Resources are as follows:
Ref. Landscape Resources Extent (m
2
)
LR1 VEGETATION
LR1-1 Mangrove 1,268,814
LR1-2 Brackish Marsh 216,600
LR1-3 Wooded Area 9,068
LR1-4
Reed (within Gei Wai and Rain-fed Pond)
N.A.
LR2 WATER BODIES (HYDROLOGY)
LR2-1 Brackish Gei Wai 1,626,739
LR2-2 Rain-fed Pond 492,035
LR2-3 Commercial Fishpond 1,668,279
LR2-4 Channelised Watercourse 10,064
LR2-5
Watercourse
170,241
4 | Page
LR2-6 Buffalo Marsh 20,000
LR3 PLANTING SURROUNDING DEVELOPMENT AREA
LR3-1 Planting surrounding Development Area 550,464
3.1.3 Photographs of the LRs as shown in Figure 9.3 of the approved EIA report are noted.
Descriptions of the baseline condition of the LRs in Section 9.5.3 to Section 9.5.13 of the
approved EIA report are as follows:
LR1 – Vegetation
3.1.4 LR1-1 Mangrove
This is the most extensive vegetation type within the 500m Assessment Area. The entire
LR1-1 falls within Mai Po Inner Deep Bay Ramsar Site. A Ramsar Site is a designated
wetland site considered to be of internationally importance under the Ramsar Convention (an
intergovernmental treaty signed on 2 February 1971 in the city of Ramsar in Iran and entered
into force in 1975). Most of LR1-1 occurs within the MPNR outside the Boundary Fence.
It forms a part of the largest mangrove community in Hong Kong. Dominant species include
the mangrove trees Kandelia obovata and Aegiceras corniculatum, and climbers such as
Derris trifoliata and Paederia scandens. LR1-1 is a unique natural landscape in the Deep
Bay Area with minimal human intervention. It is considered to have low ability to
accommodate change arising from developments. As part of the Ramsar Site, LR1-1 is
considered to be of regional importance and the sensitivity of LR1-1 is considered to be High.
3.1.5 LR1-2 – Brackish Marsh
The brackish marshes are located at the banks of the natural watercourses running
between Shek Shan and Mai Po, as well as along the southeastern perimeter of MPNR. LR1-
2 falls entirely within Mai Po Inner Deep Bay Ramsar Site. These brackish marshes are
subject to tidal influence and are dominated by marsh ferns including Mangrove Fern
Acrostichum aureum and Interrupted Tri-vein Fern Cyclosorus interruptus, wetland plant
species Eichhornia crassipes, Brachiaria mutica and Ipomoea aquatica, and interspersed with
patches of reeds (Phragmites australis). As a unique natural landscape in the Deep Bay Area
with minimal human intervention, LR1-2 is considered to have low ability to accommodate
change arising from developments. LR1-2 is considered to be part of the regionally
importance landscape resources of the Ramsar Site. Due to its high naturalness and unique
nature, LR1-2 is considered to be of High sensitivity to change.
5 | Page
3.1.6 LR1-3-Wooded Area
LR1-3 refers to the two wooded patches outside the Project site, one at Shek Shan within
MPNR, and the other on the knoll at Tam Kon Chau Police Post and its adjacent area next to
PSFSC. LR1- 3 falls within Mai Po Inner Deep Bay Ramsar Site. The wooded area at Shek
Shan is small and isolated. It is dominated by naturally regenerated native tree species such
as Ficus microcarpa, Ficus tinctoria and Ficus subpisocarpa. The wooded area at Tam Kon
Chau is subject to higher levels of human disturbance as evidenced by the presence of
household waste and construction materials in the woodland understory. This wooded area is
dominated by typical native tree species of woodland fringe areas, including Macaranga
tanarius var. tomentosa, Microcos nervosa, Ficus elastica and Ficus microcarpa, and
common fruit trees such as Litchi chinensis and Sygium jambos. Both of these wooded areas
are small in size and very common and widespread features in Hong Kong. LR1-3 is readily
re-creatable through replanting. As such, it is considered to have a medium ability to
accommodate change arising from developments. The sensitivity of LR1-3 is considered to
be Low.
3.1.7 LR1-4 – Reed
LR1-4 is derived from colonization of reed Phargmites australis into the water bodies
(brackish gei wai or rain-fed ponds). With varying water level due to seasonal changes and
active management, the extent of reed within these water bodies can vary from time to time.
LR1-4 is readily re-creatable through replanting or natural recolonization. As such, it is
considered to have a medium ability to accommodate change from developments. The
sensitivity of LR1-4 is considered to be Medium given it is a natural component of the existing
ponds and within the regionally important Rasmar Site.
LR2 Water Bodies (Hydrology)
3.1.8 LR2-1 Brackish gei wai
Brackish gei wai is the most dominant LR type within the Project Site and within the boundary
of Mai Po Inner Deep Bay Ramsar Site. These water bodies are connected with the tidal
water of Deep Bay through operational sluice gates, and are managed either to rear shrimps
and fish following traditional practices to provide food for birds, or to provide shallow-water
habitats for roosting of waterbirds in MPNR. Some of the gei wai ponds are dominated by
mangrove stands such as Kandelia obovata and Aegiceras corniculatum, whilst in their
centres there are small tree islands formed by naturally established tree species such as Ficus
subpisocarpa, Macaranga tanarius var. tomentosa and the exotic tree Melia azedarach. The
bunds between ponds and gei wai are varying in width and height dominated by grasses
Panicum spp. and common tree and shrub species such as Macaranga tanarius var. tomentosa,
Melia azedarach and Ficus spp. Brackish gei wai is a unique landscape feature in Mai Po
6 | Page
and the largest area of shrimp culture in Hong Kong, albeit this is no longer undertaken for
commercial purposes. The traditional management practices of these tidal shrimp ponds
form a unique landscape feature. In view of its uniqueness in the Deep Bay area, LR2-1 is
considered to have low ability to accommodate change arising from developments. LR2-1
constitutes a key part of the Ramsar wetland which is considered of regional importance.
The sensitivity of LR2-1 is considered to be High.
3.1.9 LR2-2 – Rain-fed Ponds
These ponds are located within the Project Site and Mai Po Inner Deep Bay Ramsar Site, vary
in water depth and contain a mosaic of microhabitats such as open water, stands of reeds,
sedges, waterlilies and small tree islands, which are actively managed areas to provide
roosting and feeding sites for waterbirds and a wide range of wildlife species in MPNR. The
pond bunds are dominated by common tree species such as Hibiscus tilaceus, Celtis sinensis,
Cerbera manghas, Casuarina equisetifolia and Macaranga tanarius var. tomentosa. Due to
the unique composition and layout of LR2-2, and being a key part of the internationally
important Ramsar Site and as a unique landscape feature in the Deep Bay area, it is considered
to have low ability to accommodate change from developments. LR2-2 is considered to have
High sensitivity to change and regionally important landscape resources.
3.1.10 LR2-3 – Commercial Fish Ponds
This LR is comprised of mostly active fish ponds and a small number of abandoned fish ponds
present both within (at Shek Shan) and outside the MPNR, all within Mai Po Inner Deep Bay
Ramsar Site. The fish ponds form extensive clusters at Lut Chau, Pak Hok Chau, Tam Kon
Chau and the western area of Mai Po. The pond bunds of the active fish ponds are dominated
by grassy vegetation (such as Brachiaria mutica and Panicum maximum), planted fruit trees
(Litchi chinensis, Dimocarpus longan and Clausena lansium) which are typical pond bund
vegetation in village areas. The abandoned ponds have been progressively overgrown with
vegetation such as grasses, reeds Phragmites australis and/or reedmace Typha angustifolia,
with scattered trees such as Macaranga tanarius var. tomentosa, Melia azedarach and
Hibiscus tiliaceus along the bunds. Although commercial fishponds are man-made/
modified landscape features and are not uncommon in rural areas, these extensive fishpond
clusters are the largest in Hong Kong and form a unique LR in the district context. In view
of its man-made/ readily re-creatable nature LR2-3 is considered to have medium ability to
accommodate change arising from developments. The overall sensitivity of LR2-3 is
considered to be Medium.
3.1.11 LR2-4 – Channelised Watercourse
This LR refers to the only channelised watercourse in the Assessment Area located in the
Fairview Park residential estate. It is an artificial feature with a concrete surface
7 | Page
occasionally colonized by wetland plant species. This type of LR is very common in Hong
Kong and offers limited greening opportunities. As an entire man-made and common
feature in the developed areas, LR2-4 is considered to have high ability to accommodate
change arising from developments. The sensitivity of LR2-4 is considered to be Low.
3.1.12 LR2-5 – Watercourse
LR2-5 refers to those natural watercourses of varying sizes connecting different types of
wetlands and providing drainage to the Assessment Area. LR2-5 is entirely within Mai Po
Inner Deep Bay Ramsar Site. The riparian vegetation are naturally established dominated
by species including herbs Cyperus malaccensis, Brachiaria mutica and Ludwigia
hyssopifolia, mangal vegetation Acrostichum aurreum and Acanthus ilicifolius and some tree
and shrub species such as Morus alba, Melia azedarach and Musa x paradisiaca. LR2-5 is
a fairly common feature in the New Territories and is largely natural but might have been
subject to minor modifications (e.g. channelization/ drainage diversion works at intervals to
connect to existing drainage systems). As such, LR2-5 is considered to have medium ability
to accommodate change arising from developments. ILR2-5 is considered to have Medium
sensitivity to change.
3.1.13 LR2-6 – Buffalo Marsh
LR2-6 (pond no. 17b) of approximately 20,000 m
2
was previously a rain-fed pond which was
overgrown with spreading reed with little aquatic plants. As a reed control experiment,
habitat enhancement work had been implemented by WWF in pond no. 17b since 2020 to
remove excessive reeds. Water buffalos had also been introduced to control reed growth and
vegetation height through grazing. LR1-6 was found containing some water in low-lying
area portions and little vegetation during the recent site visit. As an actively managed,
almost drained pond with little vegetation and low amenity, LR2-6 is considered to have high
ability to accommodate change and Low sensitivity to change from developments.
LR3 – Planting Surrounding Development Area
3.1.14 LR3-1 – Planting Surrounding Development Area
LR3-1 mainly refers to the existing plantings in residential areas at Fairview Park and Palm
Springs, a few village houses next to the MPNR’s entrance, other associated man-made
facilities (e.g. PSFSC) in the G/IC zone, and any man-made features (e.g. paved foot-paths)
and facilities in MPNR. Landscape resources such as trees/ shrubs in this category is found
surrounding/ adjacent to buildings, walls, roads, car parks, and open space, etc. Vegetation in
the developed areas is confined to the open space in the residential estates and roadside
plantings, dominated by ornamental species such as Lagerstroemia speciosa, Bauhinia x
blakeana, Caryota maxima and Archontophoenix alexandrae and fruit tree species. This
type of man-made landscape resources is common and widespread throughout Hong Kong,
8 | Page
and is subject to on-going modifications/ redevelopment and undergoing small-scale changes.
It is considered to have high ability to accommodate change. Sensitivity of LR3-1 is
considered as Low.
Existing Trees within Project Site
3.1.15 The Updated Tree Survey Report prepared in March 2021 which was included in the
approved EIA Report, a total of 383 trees of 22 species were found within the Project Site.
No registered or potentially registrable Old and Valuable Tree (OVT) or rare/ protected tree
species were recorded within the Project Site. In general, the conditions of the trees within
the Project Site were found to be fair to poor. The average tree height was found to be 9m.
The dominant native tree species are Celtis sinensis and Hibiscus tiliaceus, and the main
exotic plantation species is Casuarina equisetifolia.
3.1.16 The tree species composition within the survey area as listed in App. D of the approved EIA
report is summerised as follows:
Scientific Name
Chinese
Common
Name
Origin
Number of
Trees
% of Trees
1. Albizia lebbeck
大葉合
Exotic
5 1.3%
2.
Artocarpus
heterophyllus
菠蘿蜜
Exotic
1 0.3%
3.
Bridelia
tomentosa
土蜜樹
Native
2 0.5%
4.
Casuarina
equisetifolia
木麻黃
Exotic
51 13.3%
5. Celtis sinensis
朴樹
Native
66 17.2%
6.
Cerbera
manghas
海杧果
Native
34 8.9%
7. Dead tree
死樹
NA 9 2.3%
8.
Dimocarpus
longan
龍眼
Exotic
1 0.3%
9. Ficus microcarpa
細葉榕
Native
10 2.6%
10.
Ficus
subpisocarpa
筆管榕
Native
31 8.1%
11. Ficus virens
大葉榕
Native
1 0.3%
12.
Heritiera
littoralis
銀葉樹
Native
4 1.0%
13.
Hibiscus
tiliaceus
黃槿
Native
39 10.2%
14. Ilex rotunda
鐵冬青
Native
1 0.3%
9 | Page
Scientific Name
Chinese
Common
Name
Origin
Number of
Trees
% of Trees
15. Kandelia obovata
秋茄樹
Native
17 4.4%
16. Litchi chinensis
荔枝
Exotic
1 0.3%
17. Litsea glutinosa
潺槁樹
Native
3 0.8%
18.
Macaranga
tanarius var.
tomentosa
血桐
Native
34 8.9%
19.
Melaleuca
cajuputi subsp.
cumingiana
白千層
Exotic
1 0.3%
20. Melia azedarach
Native
53 13.6%
21. Morus alba
Native
1 0.3%
22.
Sapium
sebiferum
烏桕
Native
15 3.9%
23.
Sterculia
lanceolata
假蘋婆
Native
3 0.8%
Total
383
100%
Landscape Character Areas (LCAs)
3.1.17 A total of four LCAs were identified within the 500m Assessment Area as listed in Table 9-
4 of the approved EIA Report and described in the following sections.
LCA
Extent (m
2
)
LCA1
Comprehensive Residential Development Area: Fairview Park
and Palm Springs
548,620
LCA2
Inter-tidal Coast Landscape: Mai Po Nature Reserve (Frontier
Closed Area)
1,298,286
LCA3 Offshore Water Landscape: Shan Pui River and Deep Bay 45,075
LCA4
Rural Coastal Plain Landscape: Mai Po Nature Reserve and
Adjacent Ponds
4,253,713
3.1.18 Photograph of the LCAs as shown in Figure 9.5 of the approved EIA report are noted.
Descriptions of the baseline condition of the LCA in Section 9.5.19 to Section 9.5.22 of the
approved EIA report are as follows:
10 | Page
3.1.19 LCA1 Comprehensive Residential Development Area: Fairview Park & Palm Springs
LCA1 is characterized as ‘Comprehensive Residential Development Area’. It comprises
two major low-rise residential development areas (Fairview Park & Palm Springs). They
consist of generally low-rise buildings with generous soft landscape provision. The
Landscape Value Map of Hong Kong categorizes it as ‘High (Qualified)’ in value. Quality
and maturity of LCA1 is considered high given its generous greenery provision and active
management to optimize the aesthetic value. LCA1 is considered a common landscape
character in the New Territories (i.e. of low rarity) and it has high ability to accommodate
change through active management. The sensitivity of LCA1 is considered as Low when it
is subject to potential impacts from low-rise developments.
3.1.20 LCA2 Inter-tidal Coast Landscape: Mai Po Nature Reserve (Frontier Closed Area)
LCA2 is characterized as Inter-tidal Coast Landscapeand is largely covered in Tai Long Kei
and Shek Shan SSSI. Lying between the high and low water tidal levels, it comprises
extensive mangrove habitats. As mangrove supports high biodiversity from the ecological
perspective, as well as being rated as Highin value in the Landscape Value Map of Hong
Kong, quality and maturity of LCA2 is considered high. Being designated as a SSSI, LCA2
is an uncommon landscape character both locally and internationally. LCA2 is considered
to have low ability to accommodate change arising from developments, and its sensitivity is
generally considered as High when it is subject to potential impacts from most types of
developments.
3.1.21 LCA3 Offshore Water Landscape: Shan Pui River and Deep Bay
LCA3 is characterized as Offshore Water Landscapewhich refers to the open water leading
from Shan Pui River entering Deep Bay. It forms part of the Mai Po Ramsar site and part of
Lut Chau SSSI and thus considered to be of regional importance. LCA3 is a marine LCA
considered as High in value in the Landscape Value Map of Hong Kong as it is
predominately undeveloped and natural, with high quality and maturity. There is only a
small portion of this LCA lying along the south western margin of the 500m Assessment Area.
LCA3 is considered to be of high sensitivity to change arising from reclamation, quarry or
landfill works which are not involved in this Project.
3.1.22 LCA4 Rural Coastal Plain Landscape: Mai Po Nature Reserve and Adjacent Ponds
LCA4 is characterized as ‘Rural Coastal Plain Landscape’ and includes the majority of Tai
Long Kei and Shek Shan SSSI, part of Lut Chau SSSI and some areas of the CA zone. It
comprises commercial fishponds, brackish marshes as well as gei wai. LCA4 is rated as
“High” in value in the Landscape Value Map of Hong Kong. As it comprises an extensive
11 | Page
plain of wetland mosaic, it is considered of high quality and amenity and an uncommon
landscape character area in Hong Kong. The Project Site is entirely within this LCA4.
LCA4 is subject to routine management for conservation purposes. It is considered to be of
medium ability to accommodate change. LCA4 is considered to have Medium sensitivity to
change due to the proposed works (low-rise developments) of the Project.
Visual Sensitive Receivers (VSRs)
3.1.23 The approved EIA report identified 3 types of VSRs within the Zone of Visual Influence, i.e.
Functional VSRs, Leisure VSRs and Residential VSRs. The locations of VSRs are
indicated on Figure 9.6-1 to Figure 9.6-3 of the approved EIA report are noted. Detailed
descriptions of these VSRs in the approved EIA report are as follows:
Functional VSRs
3.1.24 Functional VSRs generally refer to those viewers who view the Project from their workplaces,
institutional and educational buildings. These viewers are generally more focused on their
work or the educational activities that they are engaged in, and are considered to be relatively
less sensitive to change compared to Residential VSRs. A total of three Functional VSRs
were identified (all are present in very few numbers), including the workers from commercial
fish ponds (F-1), staff/workers at MPEC (although this is not a true “educational building”
such as a school or university) (F-2) and workers along the pond bund of MPNR near Pond
No. 20 (F-3).
3.1.25 For the workers of commercial fish ponds (F-1), the only visible Project Element would be
a portion of the proposed footpaths along the existing visitor route. Other Project Elements
would be significantly screened off by existing tall trees at MPNR. As F-1 can enjoy 360
degrees of open outdoor view of good amenity value and can possibly view the Project
Elements at ground level, the sensitivity of F-1 to visual change as a result from the Project
is considered to be Low.
3.1.26 F-2 refers to a few WWF staff who are working at MPEC and can view a small portion of
the works areas of the new footpaths from the small windows or the platform on the second
floor of MPEC. F-2 can glimpse the Project Site when they travel to their workplace.
Sensitivity of F-2 is considered to be Low.
3.1.27 F-3 refers to the very few WWF field workers and researchers working along the pond bund
near Pond No. 20. Views of F-3 are intermittently restricted by existing trees at intervals and
they can only view the proposed TH2 and the new access when they come close to the Project
site. F-3 is considered to have Medium sensitivity to visual change due to the Project.
12 | Page
Leisure VSRs
3.1.28 Leisure VSRs are viewers who are enjoying leisure, cultural, recreational and/or educational
activities and their views could be easily distracted by the immediately adjacent amenity
landscapes or activities they are engaged in. Leisure VSRs in this Project refer to the visitors
of MPNR; and their views and sensitivity can vary according to their locations: visitors just
outside the entrance of MPNR (L-1) are considered to have Low sensitivity to the Project
as they can only glimpse a tiny portion of the Project site (the proposed footpaths). After the
visitors enter the MPNR and walk along the visitor route (L-2), they can partially view the
proposed footpaths and TH3 during construction phase(s) and all other development
components during the operation of Project, with most of the views being intermittently
blocked by existing trees. The visitors (L-3) are considered to be least sensitive when they
are bird-watching at the existing tower hide TH1, from which they are only expected to
notice minor changes due to the proposed works at TH3 approximately 100m from TH1.
Sensitivity of L-2 and L-3 to visual change due to the Project is considered to be Medium
and Low respectively.
Residential VSRs
3.1.29 Residential VSRs (R-1) refers to the very few village residents next to the entrance of
MPNR. R-1 cannot view the Project site from their home(s). However, R-1 can glimpse a
tiny portion of the proposed footpaths at the entrance of MPNR when they are travelling
home. Sensitivity of R-1 to visual change due to the Project is considered to be Low.
3.2 Methodology of Baseline Review
3.2.1 In accordance with Section 8.3.1 of the EM&A Manual, the baseline report shall be prepared
to check, record and report the status of the Landscape Resources (LRs) and Landscape
Character Areas (LCAs) within the works areas and the Visually Sensitive Receivers
(VSRs) within the visual envelope. The reviewing procedures and criteria described in
Section 8 of the EM&A Manual are adopted for this landscape baseline review.
3.2.2 Site visits were conducted on 3rd and 4th of March, 2023 to review the baseline landscape
conditions. A follow-up tree survey of the Project site was conducted on 10th and 13th of
March, 2023. Further site visits on 24th March 2023 for taking aerial photos of the area.
13 | Page
3.3 Findings
3.3.1 The area within and immediately adjacent to the Project site and works area is found to be
surrounded by commercial fish ponds, mangrove, marshes, reed fields, residential
developments and scattered tree groups and vegetations. The area is consistent with the
findings and descriptions of the identified LRs, LCAs and VSRs within the visual envelope
in the EIA report. There are also no identifiable new LRs, LCAs and VSRs in the visual
envelope that have not been assessed in the approved EIA report.
LR1-1 Mangrove
3.3.2 As observed during the site visit on 3rd of March, 2023, mangrove as identified as LR1.1 in
the approved EIA report, is consistent with the baseline conditions described in Section
9.5.3 of the approved EIA report. Photographic view of the existing conditions of LR1.1
and photograph of LR1.1 as shown in Figure 9.3.1 of the approved EIA report are illustrated
in Appendix B for easy comparison.
LR1-2 – Brackish Marsh
3.3.3 As observed during the site visit on 3rd and 4th of March, 2023, the area that was identified
as LR1.2 Brackish Marsh in the approved EIA report is overgrown with marsh ferns
including Mangrove Fern Acrostichum aureum and Interrupted Tri-vein Fern Cyclosorus
interruptus, wetland plant species Eichhornia crassipes, Brachiaria mutica and Ipomoea
aquatica, and interspersed with patches of reeds (Phragmites australis). The existing
condition of LR1.2 is consistent with the baseline conditions described in Section 9.5.4 of
the approved EIA report. Photographic view of the existing conditions of LR1-2 and
photograph of LR1.2 as shown in Figure 9.3.1 of the approved EIA report are illustrated in
Appendix B for easy comparison’.
LR1-3 – Wooded Area
3.3.4 As observed in the site visit on 3rd of March, 2023, the two wooded patches as identified as
LR1-3 Wooded Area in the approved EIA report are still intact. The condition of the
small wooded area at Shek Shan within MPNR is consistent with the baseline conditions
described in Section 9.5.5 of the approved EIA report. The area is still dominated by
naturally regenerated native tree species such as Ficus microcarpa, Ficus tinctoria and Ficus
subpisocarpa. The other knoll located at Tam Kon Chau Police Post and its adjacent area
next to PSFSC is also found consistent with the baseline conditions described in Section
9.5.5 of the approved EIA report. The area shows human disturbance as evidence by
presence of household waste and construction materials in the woodland understory.
Typical native tree species of woodland fringe areas, including Macaranga tanarius var.
14 | Page
tomentosa, Microcos nervosa, Ficus elastica and Ficus microcarpa, and common fruit trees
such as Litchi chinensis and Sygium jambos are observed. Photographic view of the
existing conditions of LR1-3 and photograph of LR1-3 as shown in Figure 9.3.1 of the
approved EIA report are illustrated in Appendix B for easy comparison.
LR1-4 – Reed
3.3.5 As verified in the site visit on 3rd March 2023, reed fields as identified as LR1.4 in the
approved EIA report, is consistent with the baseline conditions described in Section 9.5.6
of the approved EIA report. As observed, some of the brackish gei wai or rain-fed ponds
are overgrown with reeds, possibly due to seasonal changes of water levels. The existing
condition of LR1-4 is consistent with the baseline conditions described in Section 9.5.6 of
the approved EIA Report. Photographic view of the existing conditions of LR1-4 and
photograph of LR1-4 as shown in Figure 9.3.1 of the approved EIA report are illustrated in
Appendix B for easy comparison.
LR2-1 –Brackish gei wai
3.3.6 As verified in the site visit on 3rd March 2023, Brackish gei wai as identified as LR2-1 in
the approved EIA report, is consistent with the baseline conditions described in Section
9.5.7 of the approved EIA report. As observed, brackish gei wai with sluice gates is
functioning well. Some gei wai ponds are observed filled with water and gathered with
migrating birds. Other gei wai ponds are dominated by mangrove stands. Photographic
view of the existing conditions of LR2-1 and photograph of LR2-1 as shown in Figure 9.3.1
of the approved EIA report are illustrated in Appendix B for easy comparison.
LR2-2 – Rain-fed Ponds
3.3.7 As observed in the site visit on 3rd March 2023, rain-fed ponds as identified as LR2-2 in
the approved EIA report, is consistent with the baseline conditions described in Section
9.5.8 of the approved EIA report. As observed on 3rd march, 2023, the water levels of
these rain-fed ponds vary and might due to the dry seasons. Some of these ponds are dry
with patches of grass while others have shallow water that attracts migrating birds. Aerial
photos taken on 27th March 2023 shows some of the rain-fed ponds are filled with water.
Photographic view of the existing conditions of LR2-2 and photograph of LR2-2 as shown
in Figure 9.3.1 of the approved EIA report are illustrated in Appendix B for easy comparison.
LR2-3 – Commercial Fish Ponds
3.3.8 As observed in the site visit on 3rd March 2023, commercial fish ponds as identified as
LR2-3 in the approved EIA report, is consistent with the baseline conditions described in
Section 9.5.9 of the approved EIA report. As observed, operating commercial fish ponds
15 | Page
are presence and in some areas only steps away from the MPNR site. The observed typical
pond bunds environ and vegetations are consistent with the descriptions in Section 9.5.9 of
the approved EIA report. Photographic view of the existing conditions of LR2-3 and
photograph of LR2-3 as shown in Figure 9.3.1 of the approved EIA report are illustrated in
Appendix B for easy comparison.
LR2-4 – Channelised Watercourse
3.3.9 As verified in the site visit on 3rd March 2023, channelized watercourse as identified as
LR2-4 in the approved EIA report, is consistent with the baseline conditions described in
Section 9.5.10 of the approved EIA report. As observed, the watercourse in the Fairview
Park area is filled with water and appears to have no human activity inside the water channel.
Photographic view of the existing conditions of LR2-4 and photograph of LR2-4 as shown
in Figure 9.3.1 of the approved EIA report are illustrated in Appendix B for easy comparison.
LR2-5 – Watercourse
3.3.10 As verified in the site visit on 3rd March 2023, watercourse as identified as LR2-5 in the
approved EIA report, is consistent with the baseline conditions described in Section 9.5.11
of the approved EIA report. As observed, the watercourses are found in different areas of
the assessment area connecting different types of wetlands. The vegetation
Photographic view of the existing conditions of LR2-4 and photograph of LR2-4 as shown
in Figure 9.3.1 of the approved EIA report are illustrated in Appendix B for easy comparison.
LR2-6 – Buffalo Marsh
3.3.11 As observed in the site visit on 3rd March 2023, Buffalo Marsh as identified as LR2-6 in
the approved EIA report, is consistent with the baseline conditions described in Section
9.5.12 of the approved EIA report. As observed, the area is covered with short grass with
patches of water at the lower levels of this pond no. 17b. Two buffalos are presence in this
area. The Photographic view of the existing conditions of LR2-6 and photograph of LR2-
6 as shown in Figure 9.3.2 of the approved EIA report are illustrated in Appendix B for easy
comparison.
LR3-1 – Planting Surrounding Development Area
3.3.12 As observed in the site visit on 3rd March 2023, Planting Surrounding Development Area
as identified as LR3-1 in the approved EIA report, is consistent with the baseline conditions
described in Section 9.5.13 of the approved EIA report. As observed, trees/shrubs can be
found in the residential areas of Fairview Park and Palm Springs, at the village houses next
to the MPNR’s entrance, at other associated man-made facilities (e.g. PSFSC) in the G/IC
zone, and man-made features and facilities in MPNR. Trees/shrubs are found adjacent to
16 | Page
village houses, roads, walls, car parks and open spaces while more ornamental tree plantings
are observed in more developed areas like Fairview Park. The Photographic view of the
existing conditions of LR3-1 and photograph of LR3-1 as shown in Figure 9.3.2 of the
approved EIA report are illustrated in Appendix B for easy comparison.
LCA1 - – Comprehensive Residential Development Area: Fairview Park & Palm Springs
3.3.13 As verified in the site visit on 3rd and 4th of March 2023, Comprehensive Residential
Development Area: Fairview Park & Palm Springs as identified as LCA1 in the approved
EIA report, is consistent with the baseline conditions described in Section 9.5.19 of the
approved EIA report. The observation of this LCA is further supported with aerial photo
taken on 24th March 2023 where Fairview Park and Palm Springs in the area are consistent
with the views shown on the photos included in the approved EIA report. Photographic
view of the existing conditions of LCA1 and photograph of LCA1 as shown in Figures 9.5.1
& 9.5.2 of the approved EIA report are illustrated in Appendix C for easy comparison.
LC A2 Inter-tidal Coast Landscape: Mai Po Nature Reserve (Frontier Closed Area)
3.3.14 As observed on 3rd and 4th of March 2023 of the area, the Inter-tidal Coast Landscape: Mai
Po Nature Reserve (Frontier Closed Area) as identified as LCA2 in the approved EIA report,
is consistent with the baseline conditions as described in Section 9.5.20 of the approved EIA
report. The observation of this LCA is further supported with aerial photo taken on 24th
March 2023 where the Inter-tidal Coast Landscape is identifiable in the Mai Po Nature
Reserve and is consistent with the views shown on the photos included in the approved EIA
report. Photographic view of the existing conditions of LCA1 and photograph of LCA1
as shown in Figures 9.5. & 9.5.2 of the approved EIA report are illustrated in Appendix C
for easy comparison.
LCA3 – Offshore Water Landscape: Shan Pui River and Deep Bay
3.3.15 As observed on 3rd and 4th of March 2023, Offshore Water Landscape: Shan Pui River and
Deep Bay as identified as LCA3 in the approved EIA report, is consistent with the baseline
conditions as described in Section 9.5.21 of the approved EIA report. Although only a
small portion of this LCA lying along the south western margin of the 500m Assessment
Area as described in the approved EIA report, this LCA has received no human interference
due to its remoteness. Aerial photo taken on 24th March 2023 of the Shan Pui River and
Deep Bay area reveals consistency with the views shown on the photos included in the
approved EIA report. Photographic view of the existing conditions of LCA1 and
photograph of LCA1 as shown in Figures 9.5.1 & 9.5.2 of the approved EIA report are
illustrated in Appendix C for easy comparison.
LCA4 –Rural Coastal Plain Landscape: Mai Po Nature Reserve and Adjacent Ponds
17 | Page
3.3.16 As observed on 3rd and 4th of March 2023, Rural Coastal Plain Landscape: Mai Po Nature
Reserve and Adjacent Ponds as identified as LCA4 in the approved EIA report, is consistent
with the baseline conditions as described in Section 9.5.22 of the approved EIA report.
The commercial fishponds, brackish marshes as well as gei wai are visible and common to
the area around the Mai Po Nature Reserve. Aerial photo taken on 24th March 2023 of the
Shan Pui River and Deep Bay area reveals consistency with the views shown on the photos
included in the approved EIA report. Photographic view of the existing conditions of
LCA1 and photograph of LCA1 as shown in Figures 9.5.1 & 9.5.2 of the approved EIA
report are illustrated in Appendix C for easy comparison.
Trees
3.3.17 The App.D of the approved EIA report does not have a tree location plan and tree assessment
schedule attached to it but a summary of the tree species composition within the survey area.
383 trees were identified in the baseline tree survey prepared for the approved EIA report.
To facilitate the baseline verification of the existing trees at the Project site, an Updated
Tree Survey Report prepared for the Tree Preservation and Removal Proposal (TPRP) of
the Project in March 2022 was used for baseline verification reference. The tree species
composition within the survey area as presented in the TPRP report does not deviate much
from the tree species composition summary included in the approved EIA report. There
were a total of 381 trees with 21 tree species identified in the TPRP report. One tree
species (Ficus virens) was found absence from the TPRP report. The difference between
the two surveys was mainly due to the increase in numbers of dead trees with respective
reduction of some of the tree species. Two trees were not accounted for in the TPRP tree
survey with no explanation given on the reduction of 383 trees in the approved EIA report
to 381 trees in the TPRP report. Tree information included in App. D of the approved EIA
Report is included in Appendix F for reference. The tree survey plans and tree assessment
schedule prepared for the TPRP report is included in Appendix G for reference.
3.3.18 As verified in the baseline tree survey on 10
th
and 13
rd
of March, 2023 using the March 2022
tree survey information prepared for the TPRP report as reference, most of the trees as
identified on the Tree Location Plan of the TPRP report were found on site. 13 trees (T75
dead tree, T241 dead tree, T308 dead tree, T309 dead tree T361 dead tree, T387 dead tree,
T254 Melia azedarach, T278 Casurina equisetifolia, T326 Melia azedarach, T364 Hibiscus
tiliaceus, T396 Celtis sinensis, T404 Macaranga tanarius var. tomentosa T410 Melia
azedararch) were no longer exist at the indicated locations of the Tree Location Plan. 2
trees were found misidentified in the TPRP report (T51B & T54) and both of them should
be Ficus subpisocarpa instead of Kandelia obovata. One tree was found dead (T80 Melia
azedarach). The remaining trees were all identified at the locations as indicated on the
Tree Survey Plan of the TPRP report.
18 | Page
3.3.19 The tree species composition within the survey area as listed in App. D of the approved EIA
report, the TPRP report and baseline verification in 2023 is summerised as follows:
Scientific Name
Chinese
Common
Name
Number of
Trees
In Approved
EIA Report
(2021)
Number of
Trees In Tree
Preservation
and Removal
Proposal (2022)
Number of
Trees
In Baseline
Monitoring
2023
1. Albizia lebbeck
大葉合
5 5 5
2.
Artocarpus
heterophyllus
菠蘿蜜
1 1 1
3.
Bridelia
tomentosa
土蜜樹
2 3 3
4.
Casuarina
equisetifolia
木麻黃
51 48 47
5. Celtis sinensis
朴樹
66 65 64
6.
Cerbera
manghas
海杧果
34 34 34
7. Dead tree
死樹
9 20 15
8.
Dimocarpus
longan
龍眼
1 1 1
9. Ficus microcarpa
細葉榕
10 10 10
10.
Ficus
subpisocarpa
筆管榕
31 31 33
11. Ficus virens
大葉榕
1 0 0
12.
Heritiera
littoralis
銀葉樹
4 4 4
13.
Hibiscus
tiliaceus
黃槿
39 33 32
14. Ilex rotunda
鐵冬青
1 1 1
15. Kandelia obovata
秋茄樹
17 17 15
16. Litchi chinensis
荔枝
1 1 1
17. Litsea glutinosa
潺槁樹
3 3 3
18.
Macaranga
tanarius var.
tomentosa
血桐
34 31 30
19.
Melaleuca
cajuputi subsp.
cumingiana
白千層
1 1 1
19 | Page
Scientific Name
Chinese
Common
Name
Number of
Trees
In Approved
EIA Report
(2021)
Number of
Trees In Tree
Preservation
and Removal
Proposal (2022)
Number of
Trees
In Baseline
Monitoring
2023
20. Melia azedarach
53 51 47
21. Morus alba
1 1 1
22.
Sapium
sebiferum
烏桕
15 17 17
23.
Sterculia
lanceolata
假蘋婆
3 3 3
383
381
368
3.3.20 The baseline tree survey plans, tree assessment schedule and tree photographs are included
in Appendix D for reference.
Visual Sensitive Receivers (VSRs) and Photomontages
3.3.21 As described in the approved EIA report, the Project Site is surrounded by ponds on all sides
and can only be accessed through existing visitor routes of MPNR and some pond bunds of
the adjacent commercial fish ponds. The proposed scheme/works can be viewed only by
local VSRs, i.e. those VSRs in close proximity to the proposed Project Sites.
3.3.22 Seven representative viewpoint locations were selected and photomontages were prepared
to provide comparison between the existing views, proposals on Day 1 of operation without
mitigation, on Day 1 after mitigation, and in Year 10 after mitigation and included in the
approved EIA report. The viewpoint locations and the photomontages were presented in
Figure 9.7 and Figure 9.8 of the approved EIA report are noted. Present views of the seven
representative viewpoints of the photomontages and the representative viewpoints of the
photomontages included in the approved EIA report are illustrated in Appendix E for easy
comparison.
3.3.23 The descriptions for Photomontage Key Viewpoint VP01 in the approved EIA report is as
follow:
The viewpoint VP01 represents a view from VSRs just outside the entrance of MPNR,
including the visitors of MPNR (L-1) and the nearby villagers (R-1) just passing by the
entrance who can both view a tiny portion of the proposed footpaths. These VSRs are
expected to notice negligible changes due to the conversion of the hard paved footpath into
20 | Page
wooden boardwalks. With the responsive design of the new footpaths, the overall visual
impacts on these VSRs are considered to be Acceptable and potentially Beneficial.
3.3.24 As observed during the site visit on 3rd March, 2023 from approximate the viewpoint
selected for producing the photomontages the entrance of MPNR, the baseline landscape
condition of the areas within and adjacent to the Project site and works area remains
unchanged since the EIA stage. The views of the Project site and adjacent areas from
identified VSR are also expected to have remained unchanged.
3.3.25 The descriptions for Photomontage Key Viewpoint VP02 in the approved EIA report is as
follow:
The viewpoint VP02 represents a typical view from the workers of commercial fishponds
(i.e. F- 1). Although F-1 can walk along the pond bund immediately linked with the
existing visitor route proposed for the new footpaths, it is expected that F-2 are more
frequently working between the fishponds at considerable distances from the new
footpaths. As illustrated with the photomontage, F-2 will notice negligible changes due to
the construction of new footpaths which are located at ground level and to be screened off
by existing vegetation. The visual impacts on F-2 are considered Insubstantial in the
absence of mitigation, and Acceptable during construction and operation of Project when
mitigation measures are implemented.
3.3.26 As observed during the site visit on 3rd March, 2023 from approximate the viewpoint of the
commercial fish ponds (view form both VSRs F-1 and F-2), the baseline landscape condition
of the areas within and adjacent to the described fish ponds remains unchanged since the
EIA stage. The views of the Project site and adjacent areas from identified VSR are also
expected to have remained unchanged.
3.3.27 The descriptions for Photomontage Key Viewpoint VP03 in the approved EIA report is as
follow:
The viewpoint VP03 represents a typical view seen by visitors who are bird-watching in the
existing Tower Hide (TH1)(i.e. L-3) when looking towards the location of the proposed TH3.
As shown in the photomontage, the proposed TH3 is located some 100m from L-3 who are
expected to notice negligible changes due to the Project when these VSRs are concentrating
on their bird-watching activities. The overall visual impacts on L-3 are considered to be
Insubstantial without mitigation and Acceptable when mitigation measures are implemented.
3.3.28 As observed during the site visit on 3rd March, 2023 looking towards the location of the
proposed TH3 from the existing Tower Hide (TH1), the baseline landscape condition of the
areas within and adjacent to the described TH3 remains unchanged since the EIA stage.
21 | Page
The views of the Project site and adjacent areas from identified VSR are also expected to
have remained unchanged.
3.3.29 The descriptions for Photomontage Key Viewpoint VP04 in the approved EIA report is as
follow:
The viewpoint VP04 represents a typical view from visitors of MPNR (L-2) and staff of
MPEC (F-2) who travel to work at the entrance of MPEC and be able to view a small portion
of the new footpaths. As shown in the photomontage, the finishes of the new footpaths appear
to fit in well with the existing natural environments. These VSRs are expected to notice
negligible visual changes with the responsive design of the new footpaths.
3.3.30 As observed during the site visit on 3rd March, 2023 from approximate the viewpoint at the
entrance of the MPEC (view form both VSRs L-2 and F-2), towards the location of the
proposed footpath, the baseline landscape condition of the areas within and adjacent to the
proposed new footpaths remains unchanged since the EIA stage. The views of the Project
site and adjacent areas from identified VSR are also expected to have remained unchanged.
3.3.31 The descriptions for Photomontage Key Viewpoint VP05 in the approved EIA report is as
follow:
The viewpoint VP05 represents a view the workers along the pond bund of MPNR near gei
wai No. 20 (i.e. (F-3) who can view the proposed new access path connecting the proposed
Tower Hide TH2 when they come close to the Project elements. F-3 are expected to notice
a Medium level of visual changes and experience Moderate impacts from the construction
of the new access without mitigation (in the absence of screen planting). As illustrated in the
photomontages Day 1 and Year 10 of project operation, the view of the new access path will
be significantly softened and screened off by proposed bamboo planting on both sides of the
path. The overall visual impacts on F-3 are considered to be Acceptable when mitigation
measures are in place.
3.3.32 As observed during the site visit on 3rd March, 2023 from approximate the viewpoint along
the pond bund of MPNR near gei wai No. 20 of VSR F-3 towards the proposed new access
path connecting the proposed Tower Hide TH2, the baseline landscape condition of the areas
within and adjacent to the described proposed TH2 remains unchanged since the EIA stage.
The views of the Project site and adjacent areas from identified VSR are also expected to
have remained unchanged.
3.3.33 The descriptions for Photomontage Key Viewpoint VP06 and VP07 in the approved EIA
report is as follow:
22 | Page
The viewpoints VP06 and VP07 represent medium to long ranged views from distant viewers
who can be occasional visitors or staff of MPNR. As illustrated in the photomontages, the
viewers are not expected to perceive any noticeable visual changes as a result of the Project.
3.3.34 As observed during the site visit on 3rd March, 2023 from approximate the viewpoints of
VP06 and VP07, that represent medium to long range views from distant viewers who can
be occasional visitors or staff of MPNR, towards the views of the proposed new Tower
Hides, TH2 and TH3. The baseline landscape condition of the areas within and adjacent
to the described proposed TH2 and TH3 remains unchanged since the EIA stage. The
views of the Project site and adjacent areas from identified VSR are also expected to have
remained unchanged.
3.4 Conclusion
By reviewing relevant information from the approved EIA Report and conducting a site visit
on 3
rd
& 4
th
March 2023, and tree surveys on 10
th
& 13
th
March 2023, and further site visit
on 24
th
March 2023, it is confirmed that the baseline condition of the area within and
immediately adjacent to Mai Po Nature Reserve and works area does not have any
significant change since the EIA stage. The visual views of these areas from the VSRs are
therefore expected to remain similar. Amendments in the design of the landscape and visual
mitigation measures as recommended in the approved EIA Report and EM&A Manual are
therefore not required.
The bi-weekly monitoring and audit shall check those Landscape and Visual Mitigation
Measures for construction phase are fully conformed by the contractor and any non-
conformity shall be reported according to the ‘Site Inspection / Audit requirement and
procedure of the EM&A manual.
23 | Page
4. WATER QUALITY
4.0.1 As part of the EM&A programme, baseline monitoring is required for determining the ambient
environmental conditions. Baseline monitoring for water quality was conducted in periods
from 4th March 2023 to 29th March 2023 in accordance to the approved EM&A Manual
before commencement of construction works.
4.0.2 The Baseline Monitoring Report for water quality presents the details of baseline study
including project background, monitoring methodology, monitoring results, summary of
findings and Action/Limit Levels (AL/LL) established for subsequent use in the Project
construction phase EM&A programme.
4.1 Monitoring Requirements
4.1.1 The Environmental Monitoring and Audit requirements are set out in the approved EM&A
Manual. Water quality was identified as key environmental issues during the construction
phase. A summary of the requirements (Monitoring Parameters, Time and Frequency) for
conducting baseline water quality monitoring is presented in the sub-sections below.
Table 4.1.1 Summary of Baseline Monitoring Parameters
Environmental Aspect Parameters Frequency
and period
Water Quality
Water depth
pH
Temperature in
o
C
Salinity in mg/L
Turbidity in NTU
Dissolved Oxygen (DO) in %
saturation and mg/L
Suspended Solids (SS) in mg/L
Oil and Grease (O&G) in mg/L
3 days per
week for 4
consecutive
weeks
4.1.2 According to the approved EM&A Manual, water quality monitoring should be performed at
designated monitoring stations. Layout plans showing the approved monitoring locations are
attached in Appendix H. Details regarding the two designated water quality monitoring
stations are shown in Table below:
24 | Page
Table 4.1.2 Approved Water Quality Monitoring Locations
Location EASTING NORTHING
Sluice Gate 7 822107 839868
Sluice Gate 19 821344 838681
Equipment
4.1.3 DO and water temperature should be measured in-situ by a DO/temperature meter. The
equipment should be portable and weather proof using a DC power source. It should have a
membrane electrode with automatic temperature compensation complete with a cable. The
equipment should be capable of measuring:
A DO level in the range of 0-20 mg/l and 0-200% saturation; and
A temperature of between 0 and 45 degree Celsius.
4.1.4 A portable pH meter capable of measuring a range between 0.0 and 14.0 should be provided
to measure pH under the specified conditions (e.g. Orion Model 250A or an approved similar
instrument) accordingly to the Standard Methods, APHA.
4.1.5 Turbidity should be measured in situ by the nephelometric method. The instrument should be
portable and weatherproof using a DC power source complete with cable, sensor and
comprehensive operation manuals. The equipment should be capable of measuring turbidity
between 0-1000 NTU.
4.1.6 A water sampler, consisting of a transparent PVC or glass cylinder of a capacity of not less
than two litres which can be effectively sealed with cups at both ends should be used.
4.1.7 In-situ monitoring instruments should be checked, calibrated and certified by a laboratory
accredited under HOKLAS or other international accreditation scheme before use, and
subsequently re-calibrated at 3 monthly intervals.
Table 4.1.3 Action/Limit Levels for Water Quality Monitoring
PARAMETER ACTION LEVEL LIMIT LEVEL
DO in mg/L 5th percentile of baseline data 1st percentile of baseline data
SS in mg/L 95th percentile of baseline data 99th percentile of baseline data
Turbidity in NTU 95th percentile of baseline data 99th percentile of baseline data
4.2 Event / Action Plan
4.2.1 Should there be any triggering of Action Levels, or exceedance of Limit Levels, the Event /
25 | Page
Action Plan established in the approved EM&A Manual should be followed. The Event /
Action Plan is attached below:
Table 4.2.1 Event / Action Plan for Water Quality
EVENT CONTRACTOR / ET IEC ER
Action
Level
Exceedance
1. Repeat sampling
event.
2. Inform EPD and
AFCD and confirm
notification of the
non-compliance in
writing.
3. Discuss with
contractor and the IEC
the most appropriate
method of reducing
water quality
pollution during
construction and agree
with EPD.
4. Repeat
measurements after
implementation of
mitigation for
confirmation of
compliance.
5. If non-compliance
continues, increase
measures in
appropriate method by
discussion with
contractor and the IEC
for the most
appropriate method of
reducing water quality
pollution during
construction and agree
with EPD and
1. Discuss with
Contractor/ET on
the mitigation
measures
2. Review
proposals on
mitigation
measures
submitted by
Contractor
and advise the ER
accordingly
3. Assess the
effectiveness
of the
implemented
mitigation
measures.
1. Discuss with
IEC, ET and
contractor on the
proposed
mitigation
measures;
2. Make
agreement on
the mitigation
measures to be
implemented;
3. Assess the
effectiveness of
the implemented
mitigation
measures.
26 | Page
repeat measurements
after implementation of
mitigation for
confirmation of
compliance. If non-
compliance occurs a
third time, suspend
construction works and
continue sampling until
normal water quality
resumes.
Limit Level
Exceedance
Suspend construction
works and undertake
Steps 1-4 immediately.
Construction works
should only continue
when the water quality
shows compliance
again.
Undertake Steps
1-3 immediately
Undertake Steps
1-3 immediately
and consider
and instruct, if
necessary, the
Contractor to
slow down or to
stop all or part of
the construction
works until no
exceedance of
Limit level.
4.2.2 Equipment used in baseline water quality monitoring is summarized in Table below.
Calibration certificates of equipment used are attached in Appendix I
Table 4.2.2 Equipment Used in Baseline Monitoring
Environmental Aspect Equipment Model
Water Quality Multifunctional Meter Pro DSS
4.3 Monitoring Procedure
4.3.1 Field measurement procedures for each set of the water quality measurement are as followed:
i. The DO probe of the multifunctional meter is checked by wet bulb method; the pH and
turbidity probes are checked against standard solutions. Record the checking result;
ii. Record the field condition including weather conditions and any other potential source of
interference;
iii. Lower the sampler into water body and rinse it with water in the target water body;
27 | Page
iv. Fill the sampler until adequate sample is collected. Replicate sample at each
monitoring location is required;
v. Rinse the bottles by the sample before transferring samples into containing bottles;
vi. Rinse the probe of multimeter with distilled water;
vii. Measure and record temperature, turbidity, pH value and DO of each bottle of sample;
viii. Bottles containing sample is stored temporarily in insulation box with ice until reaching
the laboratory;
4.3.2 The water samples shall be delivered to a HOKLAS laboratory as soon as possible for analysis,
which shall start the next working day after collection of samples. Analyses shall follow
standard methods as described in APHA Standard Methods for the Examination of Water and
Wastewater, 19th Edition, unless otherwise specified (APHA 2540D for SS and APHA 5520C
for O&G). The QA/QC details shall be in accordance with requirements of HOKLAS.
4.4 Data Management and QA/QC
4.4.1 The baseline monitoring data were handled by the ETs in-house data recording and
management system. Laboratory responsible for laboratory analysis would follow QA/QC
requirements as set out under HOKLAS scheme.
4.4.2 Calculation for Action/ Limit Level based on the collected water samplings is summarized
as below Table 4.4.1:
Table 4.4.1 Recommended Action & Limit Levels of Water Quality
Recommended Action & Limit Levels of Water Quality
Parameter Performance
Criteria
Monitoring Location
Sluice Gate 7 Sluice Gate 19
Dissolved Oxygen
(mg/L)
Action Level
2.85
2.47
Limit Level 2.83 2.45
Suspended Solids
(mg/L)
Action Level 99.6 120.3
Limit Level 107.9 121.7
Turbidity (NTU) Action Level 47.1 122.2
Limit Level 47.2 122.8
Remark: The following data was taken out as outlier which is not considered in the Action and
Limit Level calculation of water quality.
1. Gate 7: 21/3/2023 and 25/3/2023
2. Gate 19: 21/3/2023, 23/3/2023 and 27/3/2023
Water sampling data record is referred to Appendix K.
28 | Page
4.4.3 The in-situ monitoring data measured in the equipment were recorded by both field operators
and by the equipment itself. Laboratory analysis results were directly issued by the
designated laboratory. All data were then input into a computerized database which is
properly maintained by the ET. Cross checking between results was performed by other
personnel.
4.5 Discussion and Recommendations
4.5.1 The baseline water quality monitoring was undertaken during the period of 4th March 2023
to 29th March 2023 at approved monitoring stations. There was no construction works taken
place at the Project site during the baseline monitoring period.
4.5.2 The baseline monitoring of water quality was conducted during typical wet season in Hong
Kong. It is important to note that influence of seasonal changes should be taken into account
when interpreting monitoring data obtained during dry season.
4.5.3 Review of the baseline conditions may need to be conducted regularly, in particular during
seasonal changes. If the changes in baseline conditions are evident, the environmental
performance criteria should be re-established by agreement of the ER and IEC and submitted
to EPD for endorsement.