Environmental Team for
EP-598/2022 Mai Po Nature Reserve
Infrastructure Upgrade Project
Monthly Environmental Monitoring and
Audit Report for September 2023
REMARKS:
The information supplied and contained within this report is, to the best of our knowledge, correct at the time of printing.
Ka Shing accepts no responsibility for changes made to this report by third parties.
Ka Shing Management Consultancy Ltd. www.ka-shign.net
Unit 2, 13/F Kai Yue Commercial Building, 2C Argyle St,
Mong Kok, Kowloon
Certified By Environmental Team Leader:_____________________
(Joan Choi)
Company: Ka Shing
Management Consultancy Ltd.
WWF Hong Kong
Environmental Team for
EP-598/2022 Mai Po Nature Reserve Infrastructure Upgrade Project
Monthly EM&A Report September 2023
.
1
Table of Contents
EXECUTIVE SUMMARY ...................................................................................................................... 3
1. Introduction ..................................................................................................................... 3
2. Environmental Monitoring and Audit Progress .............................................................. 3
3. Water Quality .................................................................................................................. 3
4. Complaint Log ................................................................................................................ 3
5. Notification of Summons and Successful Prosecutions .................................................. 3
6. Reporting Changes .......................................................................................................... 3
7. Future Key Issues ............................................................................................................ 3
1. INTRODUCTION ...................................................................................................................... 5
1.1 Background .................................................................................................................... 5
1.2 Purpose of the report ...................................................................................................... 5
1.3 Project Organization ....................................................................................................... 6
1.4 Summary of Construction Works Undertaken During Reporting Month ....................... 7
1.5 Construction Programme ................................................................................................ 7
1.6 Summary of EM&A Requirement .................................................................................. 7
1.7 Status of Compliance with Environmental Permit (EP) Conditions ............................... 8
2 WATER QUALITY…………………………………………………………………………….. 9
3 ENVIRONMENTAL SITE INSPECTION ............................................................................. 10
3.1 Site Audits ..................................................................................................................... 10
3.2 Implementation Status of Environmental Mitigation Measures ................................... 10
4 ENVIRONMENTAL NON-COMPLIANCE ........................................................................... 12
4.1 Summary of Environmental Non-Compliance.............................................................. 12
4.2 Summary of Environmental Complaint ........................................................................ 12
4.3 Summary of Environmental Summon and Successful Prosecution .............................. 12
5 FUTURE KEY ISSUES ........................................................................................................... 13
5.1 Key Issues in the Coming Month .................................................................................. 13
6 CONCLUSIONS AND RECOMMENDATIONS .................................................................... 14
6.1 Conclusions ................................................................................................................... 14
6.2 Recommendations ......................................................................................................... 14
LIST OF TABLES
Table E 1
Summary Table for EM&A Activities in the Reporting Month
WWF Hong Kong
Environmental Team for
EP-598/2022 Mai Po Nature Reserve Infrastructure Upgrade Project
Monthly EM&A Report September 2023
.
2
Table 1. 1
Key Contacts of the Project
Table 1. 2
Status of Environmental Licences, Notifications and Permits
Table 1. 3
Summary Table for Status of Compliance / Required Submission under EP
Table 3. 1
Observations and Follow Up Action of Site Audit
LIST OF APPENDICES
Appendix A Location of the Project
Appendix B Site Inspection & Audit Schedules
Appendix C The Environmental Mitigation Implementation Schedule (EMIS)
Appendix D Waste Generation in the Reporting Month
Appendix E Complaint Log
Appendix F Summary of Successful Prosecution
Appendix G The Tentative Construction Programmes
WWF Hong Kong
Environmental Team for
EP-598/2022 Mai Po Nature Reserve Infrastructure Upgrade Project
Monthly EM&A Report September 2023
.
3
EXECUTIVE SUMMARY
1. Introduction
This is the 4th monthly Environmental Monitoring and Audit (EM&A) Report for the Mai Po
Nature Reserve Infrastructure Upgrade Project No. EP-598/2022. This report was prepared by Ka
Shing Management Consultancy Ltd. (Ka Shing) under “Mai Po Nature Reserve Infrastructure
Upgrade Project No. EP-598/2022” (hereinafter called the “Service Contract”). This report
documents the findings of Environmental Monitoring and Audit (EM&A) work conducted from
1st to 30
th
September 2023.
2. Environmental Monitoring and Audit Progress
The monthly EM&A programme was undertaken by the ET in accordance with the EM&A
Manual. A summary of the monitoring and audit activities during the reporting period is
presented below:
Table E 1 Summary Table for EM&A Activities in the Reporting Month
EM&A Activities
Date
Weekly Environmental Site
Inspection
5 ,12 ,19 & 26 September 2023
3. Water Quality
According to Section 4.2.8 of the EM&A Manual, the precautionary water quality monitoring
shall be carried out when foundation works are carried out at TH2 and TH3. The foundation
works of TH2 and TH3 are completed on 12 Jul 2023 and 01 Aug 2023. Precautionary water
monitoring conducted on 1st, 3rd, 5th and 8th August 2023 showed no exceedance of Action/
Limit Level. According to Section 4.2.9 of the EM&A Manual, post-construction monitoring is
not required. Therefore, water quality monitoring at Sluice Gate 7 and Sluice Gate 19 is no
longer necessary and no water quality monitoring was conducted in September 2023.
4. Complaint Log
No environmental complaint was received in the reporting period.
5. Notification of Summons and Successful Prosecutions
No notification of summons or successful prosecutions was received in the reporting period.
6. Reporting Changes
There was no reporting change in the reporting period.
7. Future Key Issues
The major site activities for the coming month include:
WWF Hong Kong
Environmental Team for
EP-598/2022 Mai Po Nature Reserve Infrastructure Upgrade Project
Monthly EM&A Report September 2023
.
4
Tower Hide Roof covering, Cladding module assemble. Tower finishes installation, E&
M conduit, Interior and exterior painting. ELV devices installation. Interior fitting-out work
Ramp path Wood decking installation, Fencing installation
Footpath Protection and Safety signage caution, Pedestal footing work, Pedestal
installation, Wood decking installation.
WWF Hong Kong
Environmental Team for
EP-598/2022 Mai Po Nature Reserve Infrastructure Upgrade Project
Monthly EM&A Report September 2023
.
5
1. INTRODUCTION
1.1 Background
1.1.1 The Mai Po Nature Reserve has served Hong Kong as one of the most valuable ecological
assets in the city, and is managed by the World Wide Fund for Nature Hong Kong (“WWF”).
WWF proposes to update of an existing concrete footpath of about 1.5m wide to a raised
wooden boardwalk of about 1.65m wide, construction of a new three-storey tower hide (TH2)
and the associated access wooden boardwalk of about 156m long and 1.65m wide; and
construction of a new three-storey tower hide (TH3) and the associated access wooden
boardwalk of about 85m long and 1.65m wide. The location of the Project as shown in the
Appendix A of this report.
1.1.2 The project site is located in Mai Po Nature Reserve (MPNR) where has been managed by
World Wide Fund for Nature Hong Kong (“WWF”) since 1984. More than 20,000 people per
year visiting the MPNR and growing in visitor numbers is anticipated. Most of the existing
facilities have been in use for more than 20 years, in order to cater for an increasing number of
visitors and providing the good condition of facilities in the future, the upgrade of
infrastructure is proposed. The WWF had completed an Environmental Impact Assessment
(EIA) and is the Permit Holder.
1.1.3 The Project under Mai Po Nature Reserve Infrastructure Upgrade Project (Register No.
AEIAR-233/2022) is approved by the EIA report and later granted an EP. The approved EIA
report described both the construction phase and operational phase.
1.1.4 Ka Shing Management Consultancy Ltd. has been commissioned by the WWF to undertake
the assignment as the Environmental Team (ET) for the Designated Project of Mai Po Nature
Reserve Infrastructure Upgrade Project.
1.1.5 In accordance with the Project EM&A Manual requirements, water quality monitoring, and
site inspections should be covered in this Contract. Overall, the EM&A works follows the
demarcation of monitoring responsibilities.
1.2 Purpose of the report
1.2.1 This is the 4
th
monthly EM&A Report which summarises the impact monitoring results and
audit findings for the EM&A programme during the reporting period from 1
st
to 30
th
September 2023.
WWF Hong Kong
Environmental Team for
EP-598/2022 Mai Po Nature Reserve Infrastructure Upgrade Project
Monthly EM&A Report September 2023
.
6
1.3 Project Organization
1.3.1 EM&A Organization
1.3.2 Different parties with different levels of involvement in the Project organization under EP no.:
EP-598/2022 include:
Project Proponent WWF Hong Kong
Contractor Mak Ko Kee Building Construction Ltd
Environmental Team (ET) Ka Shing Management Consultancy Ltd.
Independent Environmental Checker (IEC) Ove Arup & Partners Hong Kong
Limited
1.3.3 The key personnel contact names and numbers under Mai Po Nature Reserve Infrastructure
Upgrade Project and the other contact names and numbers under WWF (Hong Kong) are
summarised in Table 1.1.
WWF Hong Kong
Environmental Team for
EP-598/2022 Mai Po Nature Reserve Infrastructure Upgrade Project
Monthly EM&A Report September 2023
.
7
Table 1. 1 Key Contacts of the Project
Role
Contact Person
Phone No.
Fax No.
Project Proponent
Mr. Alex WONG
2526 1011
2161 9628
Site Agent
Mr. Kin Hung LAM
2649 1883
2647 7389
ETL
Ms. Joan CHOI
2618 2166
2120 7752
IEC
Mr. Ricky CHUI
2268 3437
2268 3380
1.4 Summary of Construction Works Undertaken During Reporting Month
1.4.1 The major site activities undertaken in the reporting month included:
Tower Hide Structure building by pre-fabrication module assemble, Roof covering,
Cladding module assemble. Structure Painting, E&M conduit, ELV devices installation
Ramp path Steel reinforcement, cast in bolt fixing, Structure building
Foot path - Protection and Safety signage caution, Pedestal footing work, Pedestal
installation, Wood decking installation
1.5 Construction Programme
1.5.1 A copy of Contractors’ construction programmes is provided in Appendix G.
1.5.2 A summary of the relevant permits, licences, and/or notifications on environmental protection
for this Project is presented in Table 1.2.
Table 1. 2 Status of Environmental Licences, Notifications and Permits
Permit / Licence No.
Valid Period
Status
From
To
1. Environmental Permit (EP)
EP-598/2022
16 Feb 2022
N/A
Valid
2. Air Pollution Control (Construction Dust) Regulation
493298
02 Jun 2023
N/A
Notified
1.6 Summary of EM&A Requirement
1.6.1 The EM&A programme requires water quality monitoring as well as environmental site audits.
The EM&A requirements are described in the following sections, including:
All monitoring parameters;
Action and Limit levels for all environmental parameters;
Event / Action Plans;
Environmental mitigation measures, as recommended in the Project EIA study final report;
and
Environmental requirements in contract documents.
WWF Hong Kong
Environmental Team for
EP-598/2022 Mai Po Nature Reserve Infrastructure Upgrade Project
Monthly EM&A Report September 2023
.
8
1.7 Status of Compliance with Environmental Permit (EP) Conditions
1.7.1 The status of statutory environmental compliance with the EP conditions under the
EIAO, submission status under the EP and implementation status of mitigation
measures are presented in Table 1.3:
Table 1. 3 Summary Table for Status of Compliance / Required Submission under EP
EP Conditions
Submission
Status
1.12
Notification of Commencement Date of
Construction
Deposit
2.1
Employment of Environmental Team
(ET)
Deposit
2.4
Employment of IEC
Deposit
2.7
Employment of Qualified Ecologist
Qualified Ecologists have
been employed to carry out
work relating to ecological
aspects
2.8
Submission of Environmental Permit (EP)
Submission Schedule
Deposit
2.9
Submission of Tree Pruning or Felling Plan
Deposit
2.11
Submission of Egretry Mitigation Measures
Plan
Deposit
2.13
Submission of Method Statement and
Management Plan for the Design and
Construction of the Wooden Boardwalk
Deposit
2.14
Submission of Water Quality Mitigation
Measures Plan
Deposit
2.15
Measures to Mitigate Ecological Impacts for
water birds and wetland-dependent species
Under implementation
2.16
Measures to Mitigate Ecological Impacts for
roost and pre-roost sites of Collared Crow
and ardeid
Under implementation
3.2(i)
Conducting baseline environmental
monitoring
Deposit
3.2(ii)
Conducting impact monitoring
The termination of water
quality monitoring on 08 Aug
2023.
3.2(iii)
carrying out remedial actions described in the
Event/Action Plans of the EM&A Manual
Under implementation
3.2(iv)
Logging and keeping records of the details of
conducting baseline and impact monitoring
Completed
3.3
Submission of copy of Baseline Monitoring
Report
Deposit
3.4
Submission of copy of Monthly EM&A
Report
On-going
4.1
Submission of electronic copies of the
Baseline Monitoring Report and Monthly
EM&A Reports
Submitted
4.2
Internet address of a dedicated web site
Submitted
4.3
The Internet website is user-friendly for the
public access
On-going
WWF Hong Kong
Environmental Team for
EP-598/2022 Mai Po Nature Reserve Infrastructure Upgrade Project
Monthly EM&A Report September 2023
.
9
2 WATER QUALITY
According to Section 4.2.8 of the EM&A Manual, the precautionary water quality
monitoring shall be carried out when foundation works are carried out at TH2 and TH3.
The foundation works of TH2 and TH3 are completed on 12 Jul 2023 and 01 Aug 2023.
Precautionary water monitoring conducted on 1st, 3rd, 5th and 8th August 2023 showed no
exceedance of Action/ Limit Level. According to Section 4.2.9 of the EM&A Manual, post-
construction monitoring is not required. Therefore, water quality monitoring at Sluice Gate
7 and Sluice Gate 19 is no longer necessary and no water quality monitoring was conducted
in September 2023.
WWF Hong Kong
Environmental Team for
EP-598/2022 Mai Po Nature Reserve Infrastructure Upgrade Project
Monthly EM&A Report September 2023
.
10
3 ENVIRONMENTAL SITE INSPECTION
3.1 Site Audits
3.1.1 Site audits were carried out by ET on weekly basis to monitor the timely implementation of
proper environmental management practices and mitigation measures on the Contract site.
3.1.2 Site audits were conducted by ET with the representative of the client’s Representative and
the Contractor on 5, 12,19 & 26 September 2023 in the reporting month. Joint site audits
with the representative of the Client representative, the Contractor and IEC were carried out
on 5 & 19 September 2023.
3.1.3 During site inspections in the reporting month, no non-compliance was identified. The
observations and recommendations made during the audit sessions are summarised in
Table 3.1.
Table 3. 1 Observations and Follow Up Action of Site Audit
Parameters
Date
Observations
Follow Up Action
Air Quality
26-Sep-23
Regular watering to the exposed
grounds and unpaved roads is
necessary. (TH2 & TH3)
Regular watering to the exposed
grounds and unpaved roads has
been used.
Water
Quality
--
No environmental deficiency was
identified during the reporting
month.
--
Ecology
--
No environmental deficiency was
identified during the reporting
month.
--
Waste /
Chemical
Management
--
No environmental deficiency was
identified during the reporting
month.
--
Permit
/Licences
5-Sep-23
No Environmental Permit displayed
at TH3.
The Environmental Permit was
displayed at TH3.
Other
5-Sep-23
The screen at TH2 is not in an
upright position.
The screen at TH2 was made to the
upright position.
12-Sep-23
The screen at TH2 is not 2m-high
as required.
The screen was made to 2m-
high at TH2.
19-Sep-23
Gap is found on the screen at TH2.
The screen was fixed.
3.2 Implementation Status of Environmental Mitigation Measures
3.2.1 According to the EIA Report, Environmental Permit and the EM&A Manual of the Project,
the mitigation measures detailed in the documents are recommended to be implemented
during the construction phase. An updated summary of the Environmental Mitigation
Implementation Schedule (EMIS) is provided in Appendix C.
WWF Hong Kong
Environmental Team for
EP-598/2022 Mai Po Nature Reserve Infrastructure Upgrade Project
Monthly EM&A Report September 2023
.
11
3.2.2 During site inspections in the reporting month, the Contractor’s readiness with the
mitigation measures against dust emission was found generally satisfactory despite some
observations/recommendations as detailed above were raised.
3.2.3 Waste generated from this Project includes inert C&D materials and non-inert C&D
materials. Non-inert C&D materials are made up of general refuse and waste that cannot be
reused or recycled and has to be disposed of at the designated landfill sites. The amount of
wastes generated by the construction works of the Project during the reporting month is
shown in Appendix D.
WWF Hong Kong
Environmental Team for
EP-598/2022 Mai Po Nature Reserve Infrastructure Upgrade Project
Monthly EM&A Report September 2023
.
12
4 ENVIRONMENTAL NON-COMPLIANCE
4.1 Summary of Environmental Non-Compliance
4.1.1 No environmental non-compliance was recorded in the reporting month.
4.2 Summary of Environmental Complaint
4.2.1 In accordance with the EM&A Manual, complaints should be referred to the ET for action.
During the complaint investigation works, the ET and IEC as established according to EP
can carry out Ad-hoc site inspections to identify the source of the complaint, review the
effectiveness of the Contractor’s remedial measures and the updated situation once
received the complaint. In addition, additional monitoring and audit can also be arranged
immediately to verify the situation if necessary. ET and IEC will also oversee the
circumstances that leading to the complaint do not recur. Moreover, ET and IEC can
cooperate efficiently with the Contractor on site for completion of the investigation.
4.2.2 There was no environmental complaint received in the reporting month.
4.3 Summary of Environmental Summon and Successful Prosecution
4.3.1 There was no successful environmental prosecution or notification of summons received
since the Project commencement.
WWF Hong Kong
Environmental Team for
EP-598/2022 Mai Po Nature Reserve Infrastructure Upgrade Project
Monthly EM&A Report September 2023
.
13
5 FUTURE KEY ISSUES
5.1 Key Issues in the Coming Month
5.1.1 The tentative construction programmes for the Project are provided in Appendix G. The
major construction activities undertaken in the coming month will include:
Tower Hide Roof covering, Cladding module assemble. Tower finishes installation, E&
M conduit, Interior and exterior painting. ELV devices installation. Interior fitting-out work
Ramp path Wood decking installation, Fencing installation
Footpath Protection and Safety signage caution, Pedestal footing work, Pedestal
installation, Wood decking installation.
5.1.2 With reference to the tentative construction programmes including the indication of
coming month construction site activities in Appendix G, potential environmental impacts
arising from the above construction activities are mainly associated with waste
management, landscape and visual and ecology. The foreseeable environmental impacts
were taken into consideration of the planned mitigation measures in the coming month.
WWF Hong Kong
Environmental Team for
EP-598/2022 Mai Po Nature Reserve Infrastructure Upgrade Project
Monthly EM&A Report September 2023
.
14
6 CONCLUSIONS AND RECOMMENDATIONS
6.1 Conclusions
6.1.1 This Monthly EM&A Report presents the EM&A work undertaken in September 2023 in
accordance with EM&A Manual.
6.1.2 Environmental site inspections were conducted on 5, 12,19 & 26 September 2023 by ET in
the reporting month. No environmental non-compliance was recorded in the reporting
month.
6.1.3 According to Section 4.2.8 of the EM&A Manual, the precautionary water quality
monitoring shall be carried out when foundation works are carried out at TH2 and TH3.
The foundation works of TH2 and TH3 are completed on 12 Jul 2023 and 01 Aug 2023.
Precautionary water monitoring conducted on 1st, 3rd, 5th and 8th August 2023 showed
no exceedance of Action/ Limit Level. According to Section 4.2.9 of the EM&A Manual,
post-construction monitoring is not required. Therefore, water quality monitoring at Sluice
Gate 7 and Sluice Gate 19 is no longer necessary and no water quality monitoring was
conducted in September 2023.
6.1.4 No environmental complaint, notification of summons or successful prosecutions was
received in the reporting month.
6.1.5 The ET would keep track on the EM&A programme to ensure compliance of
environmental requirements and the proper implementation of all necessary mitigation
measures.
6.2 Recommendations
6.2.1 According to the environmental audits performed in the reporting month, the following
recommendations were made:
1. Air Quality
Regular watering to the exposed grounds and unpaved roads has been used.
2. Permit/Licences
The Environmental Permit was displayed at TH3.
3. Other
The screen at TH2 was made to the upright position;
WWF Hong Kong
Environmental Team for
EP-598/2022 Mai Po Nature Reserve Infrastructure Upgrade Project
Monthly EM&A Report September 2023
.
15
The screen was made to 2m-high at TH2;
The screen was fixed.