Environmental Permit (EP) Submission Schedule
Date: 02 May 2023
No. of month for the Project 28
March
2023
April
2023
May
2023
June
2023
July
2023
2023
2023
2023
Report to
EPD
Tasks E.P. No. Submission = deliverable
no later than
one month
before the
of construction
of the Project
2.8 Environmental Permit (EP)
Submission Schedule
2.9 Tree Pruning or Felling Plan
2.11 Egretry Mitigation Measures Plan
2.13 Method Statement and Management
Plan for the Design and Construction
of the Wooden Boardwalk
2.14 Water Quality Mitigation Measures
Plan
At least two
weeks before
the
of construction
of the Project
3.3 and
EM&A
Manual
4.2.7
Baseline water quality monitoring
Report
3.3, and
EM&A
Manual
8.3.1
Baseline Landscape and Visual
Report
EM&A monthly
report
3.4 Within 10 working days after the end
of each month.
Final EM&A
report
NA.
Certificated by Environmental Team Leader:______________________(Joan Choi) Company: Ka Shing Management Consultancy Ltd.